Question: 3- In the following example on the (PERT) method, there is no task that depends on the task F, and the network must be closed

3- In the following example on the (PERT) method, there is no task that depends on the task F, and the network must be closed to find all the paths. Identify and discuss with which node task F should be closed? None 3 None 4 A Conduct Intenews B Questionnaires c Read Reports D Analyze Data Flows E laboduce Prototypes F Observe Reactions Perform Cost Beach H_Prepare Proposal 1 Present Pmposat ***** D 20