Question: 3. MEYER WERFT HAS RECEIVED A CONTRACT FOR A LUXURY YACHT TO BE DELIVERED IN APRIL 2022. THE YACHT IS CONSTRUCTED FROM THE FOLLOWING SIX

3.MEYER WERFT HAS RECEIVED A CONTRACT FOR A LUXURY YACHT TO BE DELIVERED IN APRIL 2022. THE YACHT IS CONSTRUCTED FROM THE FOLLOWING SIX BLOCKS:

BLOCK 1(26 WEEKS)

BLOCK 2(15 WEEKS)

BLOCK 3(10 WEEKS)

BLOCK 4(5 WEEKS)

BLOCK 5(20 WEEKS)

BLOCK 6(5 WEEKS)

BLOCKS 1 & 2 ARE SEQUENTIAL. BLOCKS 3, 4, AND 5 CAN BE DONE ANYTIME IN ANY ORDER. HOWEVER, ONLY TWO OF THEM CAN BE UNDER CONSTRUCTION SIMULTANEOUSLY. BLOCKS 1-5 MUST BE COMPLETED BEFORE BLOCK 6 CAN BEGIN. THE OPTIMUM TIDES FOR GOING DOWN THE RIVER EMS ARE MARCH 15-18, 2022 AND SEPTEMBER 15-18, 2022.

MAKE A GANTT CHART FOR THE YATCH'S CONSTRUCTION

CONVERT YOUR GANTT CHART TO A PERT DIAGRAM

WHAT IS/ARE YOUR CRITICAL PATH(S)?

WHAT IS THE LATEST DATE CONSTRUCTION CAN BEGIN? IF YOU WANTED A TWO-WEEK CUSHION FOR UNFORESEEN PROBLEMS?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Law Questions!