Question: 3 part question Powerful Paul is planning on running for congress. Mapping out his strategy to obtain the Washington DC job he determines that there

3 part question
 3 part question Powerful Paul is planning on running for congress.
Mapping out his strategy to obtain the Washington DC job he determines
that there are four tasks that must be performed. All relevant information
pertaining to these tasks is available in the table below. How much

Powerful Paul is planning on running for congress. Mapping out his strategy to obtain the Washington DC job he determines that there are four tasks that must be performed. All relevant information pertaining to these tasks is available in the table below. How much will it cost Paul to reduce the project by 4 days? $9 bazillions $10 bazillions $11 baziltions $12 bazillions Which of these activities is on the critical path for the project? 1. Activity B II. Activity C I only II only Both I and II Neither I nor II After crashing to the fullest extent possible, what is the minimum amount of time required to complete the project? 6 days 5 diys 4 days 3days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!