Question: [ 3 points ] Which time estimates are given to each activity in PERT? ( answer: A , B , or C ) C .

[3 points] Which time estimates are given to each activity in PERT? (answer: A, B, or C)
C. optimistic, pessimistic, forecasted
B. actual, optimistic, pessimistic
A. mostly likely, optimistic, pessimistic
 [3 points] Which time estimates are given to each activity in