Question: 3 Previously, the processing times at the various stations were the same regardless of the part type. Now we discover the processing times depend on
3 Previously, the processing times at the various stations were the same regardless of the part type. Now we discover the processing times depend on the particular part type as given in Table 5.5. In this table, the sequences are the same as before, but here the processing times have been added. Table 5.5: Entity Sequences and Processing Times (in Minutes) Step Part 1 Station A (Pert(2.5.8)) Station C (Pert(2.6.11) Part 2 Station A (Pert(1.3.4)). Station B (Uniform(5 to 11) Station C (Uniform(2 to 11)) Part 3 Station A (Triangular(2.5.8)) Station B (Triangular(5.9.11)) Part 4 Station B (Pert(5.9.11) Station C (Triangular (2.6.11)) Question 10: (1%). Do you think it is realistic that the processing time for Part1 on Station A might be different for Part2 on that same Station A