Question: 3 Production Lot (Batch) Size = 0 AOH =75 3 25 4 25 8 4 5 40 Forecast Customer Orders Projected OH MPS ATP 1
3 Production Lot (Batch) Size = 0 AOH =75 3 25 4 25 8 4 5 40 Forecast Customer Orders Projected OH MPS ATP 1 2 20 25 32 21 32 80 What is the available to promise for week 1? 0 75 0 55 0 43 0 22 O None of the above are correct