Question: 3 pts Question 2 Suppose a project's critical path consists of three activities, each with duration estimates as follows ... Duration Estimates (days) Activity Optimistic

3 pts Question 2 Suppose a project's critical

3 pts Question 2 Suppose a project's critical path consists of three activities, each with duration estimates as follows ... Duration Estimates (days) Activity Optimistic (a) Most Likely (m) Pessimistic (b) X 10 16 30 Y 9 15 34 Z 9 19 27 What is the standard deviation of this project's expected completion time? (Round to 2 decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!