Question: ( 3 ) Question: We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and

(3) Question: We have a project (Raise_L), with these activities in days: Activity A with duration 6 and no precedents. Activity B with duration 10 and predecess...
We have a project (Raise_L), with these activities in days: Activity A with duration 6 and no precedents. Activity B with duration 10 and predecessor. A, Activity C with duration 2 and predecessor. A, Activity D with duration 6 and predecessor B, Activity E has duration 3 and predecessors B and C, Activity F has duration 1 and predecessor D, and Activity G has duration 11 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take?
22 days
33 days
34 days
 (3) Question: We have a project (Raise_L), with these activities in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!