Question: 3. The critical path in a project network is the (1 Point) Shortest path through the network Longest path through the network Network path with
3. The critical path in a project network is the (1 Point) Shortest path through the network Longest path through the network Network path with the most difficult activities 4. Lags can be used to constrain the start and finish of an activity (1 Point) True False