3. The ES for Node A is:
| a. | 0 | |
| b. | 1 | |
| c. | 5 | |
| d. | 10 |
-
The ES for Node F is:
a. 0
b. 4
c. 11
d. 15
-
The EF for Node C is:
a. 4
b. 5
c. 11
d. 15
-
The LS for Node A is:
a. 0
b. 1
c. 5
d. 10
-
The length of the critical path is:
a. 9
b. 13
c. 19
d. There is no critical path