Question: Given this information about activity B: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount

Given this information about activity B: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is: Question 20Select one: a. 0 b. 1 c. 5 d. 6 e. 11