Question: [30 points] Consider a project with following precedence relationships and activity times . Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A --
- [30 points] Consider a project with following precedence relationships and activity times.
| Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | -- | 2 | 2.5 | 6 |
| B | -- | 10 | 11 | 12 |
| C | A | 5 | 6.5 | 11 |
| D | B, C | 11 | 13 | 15 |
| E | B | 8 | 9.5 | 14 |
| F | D | 4.5 | 5.5 | 9.5 |
| G | E | 3.5 | 5 | 6.5 |
| H | F, G | 6.5 | 7.5 | 11.5 |
- Calculate the expected activity duration (te), variance for each activity, ES, EF, LS, and LF times and the slack for each activity.
- What is the critical path for the project?
- What is the probability of completing the project in 35 weeks?
- If the activity B can be finished in 10 weeks, D in 11 weeks, and E in 8 weeks, recalculate the expected project completion time.
- Using MS Project (or any other software), create a Gantt chart for the project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock