Question: [ 3 0 points ] Consider a project with following precedence relationships and activity times. table [ [ Activity , table [ [
points Consider a project with following precedence relationships and activity times.
tableActivitytableImmediatePredecessortableOptimisticTimetableMost LikelyTimePessimistic TimeABCDEFGH
a Calculate the expected activity duration variance for each activity, ES EF LS and LF times and the slack for each activity. Show the values in a table activity schedule What is the critical path for the project? Show all work to earn credit.
b Using MS Project or any other software create a Gantt chart for the project based on ES and EF times.
c What is the probability of completing the project in weeks? Show all work to earn credit.
d If the activity B can be finished in weeks, D in weeks, and in weeks, recalculate the expected project completion time. Show all work.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock