Question: (30) QUESTION 1 Rustic Deck Project Activity Immediate Predecessor Optimistic Most Likely Pessimistic 9 --- A B C 7 10 8 11 8 10 10

(30) QUESTION 1 Rustic Deck Project Activity

(30) QUESTION 1 Rustic Deck Project Activity Immediate Predecessor Optimistic Most Likely Pessimistic 9 --- A B C 7 10 8 11 8 10 10 14 8 8 D 13 13 17 11 9 E C D F F 7 7 4 6 7 5 6 G H 1 END B 9 7 10 9 H E,G,I 1.1. Determine the expected completion time and variance for each activity. 1.2. Construct an AON network for the activities of this contract. 1.3. Determine the critical path for the project by determining the slack of each activity. (9) (11)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!