Question: QUESTION 4 A computer network company installs network points. The project manager has been very concerned with the amount of time it took to complete

QUESTION 4 A computer network company installs network points. The project manager has been very concerned with the amount of time it took to complete several recent jobs. The data obtained (all in days) for a new contract are listed in the following table:

QUESTION 4 A computer network company installs

Required:

2.1 Determine the expected completion time and variance for each activity. (8 marks)

2.2 Construct an AON network for the activities of this contract. (8 marks)

2.3 Determine the critical path for the project by determining the slack for each activity (8 marks)

2.4 What is the probability that this project will be completed in 40 days? (6 marks)

\begin{tabular}{|c|c|c|c|c|} \hline Activity & Immediate Predecessor & Optimistic & Most Likely & Pessimistic \\ \hline A & & 3 & 6 & 8 \\ \hline B & & 2 & 4 & 4 \\ \hline C & & 1 & 2 & 3 \\ \hline D & C & 6 & 7 & 8 \\ \hline E & B D & 2 & 4 & 6 \\ \hline F & A E & 6 & 10 & 14 \\ \hline G & A E & 1 & 2 & 4 \\ \hline H & F & 3 & 6 & 9 \\ \hline I & G & 10 & 11 & 12 \\ \hline J & C & 14 & 16 & 20 \\ \hline K & H & 2 & 8 & 10 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!