Question: 30. The customer has asked that you reduce activity by 2 weeks. What it have on the schedule? (8 Points) a. None. It is not

30. The customer has asked that you reduce

30. The customer has asked that you reduce activity by 2 weeks. What it have on the schedule? (8 Points) a. None. It is not on the critical path b. It will reduce the schedule like two weeks It will only work if you also reduce activity B by two weeks d. It will only work if you also reduce activity F by two weeks None of these C. e