Question: QUESTION 3 The customer has asked that you reduce activity D by 2 weeks. What impact does this have on the schedule? None. It is

QUESTION 3
The customer has asked that you reduce activity D by 2 weeks. What impact does this have on the schedule?
None. It is not on the critical path
It will reduce the schedule like two weeks
It will only work if you also reduce activity B by two weeks
It will only work if you also reduce activity F by two weeks