Question: 3.1 Using the information below, construct the PERT network, identify the critical path, and determine the slack time for each node. [10] Activity Weeks Full

3.1 Using the information below, construct the

3.1 Using the information below, construct the PERT network, identify the critical path, and determine the slack time for each node. [10] Activity Weeks Full time personnel required 3 A-B 5 A-C 3 3 B-D 2 4 B-E 3 5 C-E 3 5 D-F 3 5 E-F 6 3