+ 1. The following project is defined as follows: Use PERT/CPM to answer the following questions....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
+ 1. The following project is defined as follows: Use PERT/CPM to answer the following questions. You need to work this out manually without any software using AOA or AON network method. Activity ABCDEFGHLIEL J ACTIVITY AB AC AD BC Duration (weeks) Immediate Predecessors 10 BE CF DF 7 4 20 7 10 7 3882 15 11 EF FG 7 2 a. Construct the network for this problem b. Determine the early start, late start, early finish, late finish for each activity c. Determine the estimated project completion time and critical path d. Determine the slack for each activity e. What is the effect to the overall project if activity C takes 21 weeks and activity E takes 10 weeks to complete 2. On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager and approved by the customer is the following: NETWORK LOGIC/ TIME (Weeks) 7 10 AURRE 8 4 А 2 3 с 2 1 B.D.E. B.DE F F G.H LI G.H On August 27, 2013, the executive steering committee received the following report indicating the status of the project as of this time (end of week 8) ACTIVITY % COMPLETE ACTUAL COST TIME REMAINING (Weeks) AB AC AD BC BE a. What is the expected completion time of this project? b. What is the critical path? START ACTIVITY c. Use Earned Value to determine the status of the project as of August 27th, by determining Cost Variance, Schedule Variance, CPI, SPI and Critical Ratio ABCDE 100 60 d. Is the project ahead of schedule or behind schedule and over budget or under budget? e. What recommendations would you make for this project? 87.5 50 50 3. Given the following PERT network for modeling a new home construction by the Bonanza Development companx (activity times are given in weeks): 133 st 3 B 3 E $23,500 $19,200 DURATION ACTIVITY DURATION 6 8 CHLIEL $37,500 $8,000 $5,500 G Н F K H 10 5 0 4 1 2 1 3 1 5 3 K FINISH a) What is the critical path and expected project completion time? b) Activity J is being performed by a subcontractor, Reliable Plumbers, who is going to be 5 weeks delayed. It will cost Bonanza $2000 per week if the project is not completed on time (within the critical path length). Reliable is charging $3000 for the plumbing activity. Bonanza has three options: > Keep Reliable Plumbers 4. Consider the following project (times are in weeks): A ACTIVITY Cancel the contract with Reliable Plumbers and hire another contractor, Local Plumbers Inc. Local Plumbers will take two weeks to complete activity J and will charge $7000. Bonanza can train its own employees who are currently performing activity E to do the work. This involves a two week training period as soon as activity E is done. It is expected it will take them three weeks to perform activity J. The cost of the training is $800 per week and the cost of them doing activity J is $1000 per week. Which alternative do you recommend? Explain? ABCDEFG NORMAL CRASH TIME TIME 12 7 844244 B 12 53193 E NORMAL COST $3,000 $2,000 $4,000 $500 $5,000 $500 $5,000 F CRASH COST $5,000 $3,500 $7,000 $1,100 $8,000 $1,100 $8,000 G & What is the critical path & project completion time? b. What is the minimal cost to crash the project to 24 weeks? c. What is the minimal time and cost that the project can be crashed? 5. Refer to the earned value chart below for a specific project and answer the following questions: DOLLARS $35,000 $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $0. EARNED VALUE 6 7 TIME LINE (weeks) 8 10 12 a. Describe what occurred with schedule and cost in weeks 1 through 5 b. Between weeks 5 and 6, was the project on schedule and within cost? Explain? c. Explain what occurred between weeks 6 through 8 with regards to schedule and costs d. Describe the current status of the project (week 10) with regards to cost and schedule -BCWS BCWP ACWP a. The probability of completing the project within 20 days b. The probability of completing the project between 17 and 21 days c. The probability of completing the project within 16 days d. The number of days to complete the project within a probability of 95% Activity A M B A B с D Activity А ABCDEFGH-KLE E F G J M a. Average time and standard deviation to complete the project b. The probability that each activity is on the critical path c. The probability of completing the project within 50 weeks 1 2 4 ABBD00 8 2 4 1 7. Consider the following project below. Assume that each time has a triangular distribution with the minimum, most likely and maximum values indicated. Use simulation to determine: А Immediate Minimum Predecessor Value 2 C,E,F,G H H I J K,L Time Estimates (weeks) Most Likely Value W74A W ON W 3 8 6 3 3 3 1 3 3 10 8 6 2 43200420 00 00 61415 8 3 5 9 5 5 2 5 5 4 2 4 Maximum Value 5 7 10 8 10 7 9 3 4 6 64 10 8 6 3 6 Immediate Predecessors A B C.D B E + 1. The following project is defined as follows: Use PERT/CPM to answer the following questions. You need to work this out manually without any software using AOA or AON network method. Activity ABCDEFGHLIEL J ACTIVITY AB AC AD BC Duration (weeks) Immediate Predecessors 10 BE CF DF 7 4 20 7 10 7 3882 15 11 EF FG 7 2 a. Construct the network for this problem b. Determine the early start, late start, early finish, late finish for each activity c. Determine the estimated project completion time and critical path d. Determine the slack for each activity e. What is the effect to the overall project if activity C takes 21 weeks and activity E takes 10 weeks to complete 2. On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The contract consisted of $143,000 for labor and materials, the remaining $17,000 was profit. The contract had a scheduled start date of July 3. The network logic, as defined by the project manager and approved by the customer is the following: NETWORK LOGIC/ TIME (Weeks) 7 10 AURRE 8 4 А 2 3 с 2 1 B.D.E. B.DE F F G.H LI G.H On August 27, 2013, the executive steering committee received the following report indicating the status of the project as of this time (end of week 8) ACTIVITY % COMPLETE ACTUAL COST TIME REMAINING (Weeks) AB AC AD BC BE a. What is the expected completion time of this project? b. What is the critical path? START ACTIVITY c. Use Earned Value to determine the status of the project as of August 27th, by determining Cost Variance, Schedule Variance, CPI, SPI and Critical Ratio ABCDE 100 60 d. Is the project ahead of schedule or behind schedule and over budget or under budget? e. What recommendations would you make for this project? 87.5 50 50 3. Given the following PERT network for modeling a new home construction by the Bonanza Development companx (activity times are given in weeks): 133 st 3 B 3 E $23,500 $19,200 DURATION ACTIVITY DURATION 6 8 CHLIEL $37,500 $8,000 $5,500 G Н F K H 10 5 0 4 1 2 1 3 1 5 3 K FINISH a) What is the critical path and expected project completion time? b) Activity J is being performed by a subcontractor, Reliable Plumbers, who is going to be 5 weeks delayed. It will cost Bonanza $2000 per week if the project is not completed on time (within the critical path length). Reliable is charging $3000 for the plumbing activity. Bonanza has three options: > Keep Reliable Plumbers 4. Consider the following project (times are in weeks): A ACTIVITY Cancel the contract with Reliable Plumbers and hire another contractor, Local Plumbers Inc. Local Plumbers will take two weeks to complete activity J and will charge $7000. Bonanza can train its own employees who are currently performing activity E to do the work. This involves a two week training period as soon as activity E is done. It is expected it will take them three weeks to perform activity J. The cost of the training is $800 per week and the cost of them doing activity J is $1000 per week. Which alternative do you recommend? Explain? ABCDEFG NORMAL CRASH TIME TIME 12 7 844244 B 12 53193 E NORMAL COST $3,000 $2,000 $4,000 $500 $5,000 $500 $5,000 F CRASH COST $5,000 $3,500 $7,000 $1,100 $8,000 $1,100 $8,000 G & What is the critical path & project completion time? b. What is the minimal cost to crash the project to 24 weeks? c. What is the minimal time and cost that the project can be crashed? 5. Refer to the earned value chart below for a specific project and answer the following questions: DOLLARS $35,000 $30,000 $25,000 $20,000 $15,000 $10,000 $5,000 $0. EARNED VALUE 6 7 TIME LINE (weeks) 8 10 12 a. Describe what occurred with schedule and cost in weeks 1 through 5 b. Between weeks 5 and 6, was the project on schedule and within cost? Explain? c. Explain what occurred between weeks 6 through 8 with regards to schedule and costs d. Describe the current status of the project (week 10) with regards to cost and schedule -BCWS BCWP ACWP a. The probability of completing the project within 20 days b. The probability of completing the project between 17 and 21 days c. The probability of completing the project within 16 days d. The number of days to complete the project within a probability of 95% Activity A M B A B с D Activity А ABCDEFGH-KLE E F G J M a. Average time and standard deviation to complete the project b. The probability that each activity is on the critical path c. The probability of completing the project within 50 weeks 1 2 4 ABBD00 8 2 4 1 7. Consider the following project below. Assume that each time has a triangular distribution with the minimum, most likely and maximum values indicated. Use simulation to determine: А Immediate Minimum Predecessor Value 2 C,E,F,G H H I J K,L Time Estimates (weeks) Most Likely Value W74A W ON W 3 8 6 3 3 3 1 3 3 10 8 6 2 43200420 00 00 61415 8 3 5 9 5 5 2 5 5 4 2 4 Maximum Value 5 7 10 8 10 7 9 3 4 6 64 10 8 6 3 6 Immediate Predecessors A B C.D B E
Expert Answer:
Answer rating: 100% (QA)
Here are the stepbystep workings for the questions 1 Project network and PERT calculations a The network for the given activities is A F G H B F C E D ... View the full answer
Related Book For
Posted Date:
Students also viewed these accounting questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON (see Example 5 for either type). Then answer the following...
-
Examine the difficulty of adding a proposed lwi.drd, rsl, rs2 (Load With Increment) instruction to MIPS. Interpretation: Reg[rd] = Mem[Reg[rs1] + Reg[rs2]] 1. Which new functional blocks (if any) do...
-
Describe the purpose of an operational audit.
-
If a noncritical path activity is crashed, what happens to the overall duration of the project?
-
An incompressible fluid flows along a \(0.20-\mathrm{m}\)-diameter pipe with a uniform velocity of \(3 \mathrm{~m} / \mathrm{s}\). If the pressure drop between the upstream and downstream sections of...
-
The Western Outfitters Store specializes in denim jeans. The variable cost of the jeans varies according to several factors, including the cost of the jeans from the distributor, labor costs,...
-
According to the video "The Importance of Budgeting," budgeting is a crucial aspect of running a successful business as it helps administrators allocate resources effectively to meet their goals. It...
-
The Morton Supply Company produces clothing, footwear, and accessories for dancing and gymnastics. They produce three models of pointe shoes used by ballerinas to balance on the tips of their toes....
-
Use the method of Archimedes and a regular polygon with 12 side to approximate the value of T
-
Review the assumptions from the previous problem, and assume that it still costs 6 to produce a pack of cigarettes. a. Draw the private supply curve and the private demand curve in this market. What...
-
Assuming that a tea plantation has market power in the market for tea workers, explain how it could use that power in setting the wage rate. Draw a graph to illustrate your answer. Sri Lankas workers...
-
An employee from that organization notified us about the change in date for the event. Revise the following sentences to improve clarity and precision. Use your imagination to add appropriate words.
-
The following data have been reported for the constant-pressure heat capacity of a benzenecarbon tetrachloride mixture at 20C. On a single graph plot the constant-pressure partial molar heat capacity...
-
To smooth out swings in the business cycle, the government influences the economy through its fiscal and monetary policies. Discuss the monetary and fiscal policies that have been applied in response...
-
void process Nums(int nums[], int n) { int i=-1, j=0; for(j
-
Let X be a random variable taking on values a1, a2, . . . , pr with probabilities p1, p2, . . . , pr and with E(X) = μ. Define the spread of X as follows: This, like the standard deviation, is a...
-
What are some of the trade-offs that might be factors in designing a supply chain?
-
a. Given the following forecast and steady regular output of 550 every month, what total cost would result if overtime is limited to a maximum of 40 units a month, and subcontracting is limited to a...
-
An analyst made the following observations about whether customer service representatives were busy (B) or idle (I): a. What is the percentage of idle time? b. Given these results, how many...
-
Use equation (17.2) to establish the following distributional relationships that are helpful for calculating quantiles. a. Assume that \(y_{0}=\alpha_{1} F / \alpha_{2}\), where \(F\) has an...
-
Assume that \(y\) is normally distributed with mean \(\mu\) and variance \(\sigma^{2}\). Let \(\phi(\cdot)\) and \(\Phi(\cdot)\) be the standard normal density and distribution functions,...
-
Consider a GB2 probability density function given in equation (17.3). a. Reparameterize the distribution by defining the new parameter \(\theta=e^{\mu}\). Show that the density can be expressed as...
Study smarter with the SolutionInn App