Question: 32 . Change control systems are designed to accomplish all of the following except A . Track all changes that are to be implemented B

32 . Change control systems are designed to accomplish all of the following except A . Track all changes that are to be implemented B . Review , evaluates , and approve di sapprove proposed changes formally DO C . Identify expected effects of proposed changes on schedule and budget D. Reflect scope changes in baseline and performance measures P E . All of the above are correct