Question: 32C An activity in a project network has the following characteristics: ES 5, EF 10, and LF 14. Therefore, LS 9.0 weeks. 12.0 weeks

32C An activity in a project network has the following characteristics: ES

32C An activity in a project network has the following characteristics: ES 5, EF 10, and LF 14. Therefore, LS 9.0 weeks. 12.0 weeks 10.0 weeks 11.0 weeks Moving to another question will save this response. OL hp