Question: An activity in a project network has the following characteristics: ES = 5, EF = 10, and LF =14. Therefore, LS = . A. *
An activity in a project network has the following characteristics: ES
= 5, EF = 10, and LF =14. Therefore, LS = .
A. * 9.0 weeks.
B. 10.0 weeks.
C. 11.0 weeks.
D. 12.0 weeks.