Question: 344 Chapter 10 . Project Scheduling INTEGRATED PROJECT Developing the Project Schedule Develop an in-depth schedule for your initial project based on the Work Breakdown

344 Chapter 10 . Project Scheduling INTEGRATED344 Chapter 10 . Project Scheduling INTEGRATED344 Chapter 10 . Project Scheduling INTEGRATED344 Chapter 10 . Project Scheduling INTEGRATED

344 Chapter 10 . Project Scheduling INTEGRATED PROJECT Developing the Project Schedule Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed. You will need to complete several activities at this stage: (1) create an activity precedence diagram showing the network logic for each project activity you have identified; (2) prepare an activity duration table showing optimistic, likely, and pessimistic activity times for each task; and (3) create both the network diagram and Gantt charts for your project, indicating the critical path and all critical activities, total project duration, and all activities with float. As you prepare the activity precedence diagram, consider: 1. Have we identified opportunities to create parallel paths or are we placing too many activities directly in a serial path? 2. Is our logic correct for identifying preceding and subsequent activities? 3. Are there some clear milestones we can identify along the precedence diagram? As you prepare the activity duration table, you might wish to set it up along the following lines: Duration Activity Optimistic Likely Pessimistic Est. Duration 6 9 18 10 A B 3 8 13 8 Finally, in creating the network diagram and Gantt charts, use MS Project or a comparable scheduling te Windo software package (see examples in Figures 10.26, 10.27, and 10.28a, b, and c). Go to Settings to ad Sample Project Schedule, ABCups, Inc. Duration (in days) 1 5 4 26 Tasks Plant manager feasibility request Get technical approval Determine if additional labor needed Research equipment Determine best suppliers Meet with vendors Obtain quotations from vendors Pick equipment vendor Negotiate price and terms Obtain financing for equipment Calculate ROI Obtain required signatures Capital approved Issue purchase order Equipment being built Marketing new process Create mailer Design new brochure Update Web site Lay out plant for new equipment Note: This is a partial activity network and schedule. 21 21 21 14 7 3 3 3 10 1 40 21 15 9 9 15 Integrated Project 345 i Task Name Duration January February March April 12/21 12/28 1/4 1/1 118 1/25 1M8 1/25 2M 218 215 2122 3M 3/8 318 3M5 3122 3129 4/5 4M2 h 1 1 2 3 4 5 6 7 8 9 10 Plant mgr feasibility request 1 day Technical approval 5 days Determine add'l labor needs 4 days Research equipment 26 days Determine best suppliers 21 days Meet with vendors 21 days Obtain vendor quotes 21 days Pick equipment vendor 14 days Negotiate price and terms 7 days Obtain equipment financing 3 days Calculate ROI 3 days Obtain required signatures 3 days Capital approval 10 days Issue purchase order 1 day Equipment being built 40 days Marketing new process Create mailer 15 days Design new brochure 9 days Update web site 9 days Lay out plant for new equip 15 days 11 12 13 14 15 16 21 days 17 18 19 20 FIGURE 10.26 Partial Gantt Chart for ABCups, Inc. Project (Left Side) May June 4M2 449 4/26 573 570 577 5/24 5/31 6/7 July August 6M4 6/21 6/28 715 772 779 7/26 8:2 8/9 8/16 FIGURE 10.27 Partial Gantt Chart for ABCups, Inc. Project (Right Side) Activate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!