Question: 34a. Compute the expected value E(t) and variance V(t) for all activities Activity A B C D E F G H E(t) weeks V(t) weeks^2

34a. Compute the expected value E(t) and variance

34a. Compute the expected value E(t) and variance V(t) for all activities Activity A B C D E F G H E(t) weeks V(t) weeks^2

34b. there are three critical paths ACG, ADG, and BEH, all with expected project completion time time E(t) = 14 weeks. Compute the variance of project completion time for each path V(ACG)= V(ADG)= V(BEH)

34c. Assume that the project completion time T is normally distributed with mean E(T)=14 weeks and variance V(T) approximately by the maximum of the variances of the three individual critical paths. Determine the time X in weeks for which there is a 40% probability that the project can be completed on or before x.

34d. List all alternatives and the respective costs for shortening the project by one week and identify the best alternative that has the minimum costs. Hint there are 8 alternatives Alternative cost the best alternative is..

34e. For activity i, let Xi be the earliest finishing time and Yi be the number of weeks shortened. Formulate the linear program for minimizing the cost for shortening the project by one week

I need the answers for 34c, 34d and 34e and don't have much time. please show work and answer The attacked file is where the problem starts

34. A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity Predecessor Crash Most Most Most Cost Maximum Optimistic likely Pessimistic ($000) Crashable (a) (m) (C) per weeks week A None 1 3 11 3 1 00 None 4 5 6 4 1 5 6 7 1 2 A D 4 5 12 1 2 1 E B 6 11 2 1 1 2 15 3 B F 1 2 4 6 6 C D G 2 3 4 2 2 2 1 H EF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!