Question: 36. When delivering a project, the project manger has to balance which of the following A. Definition and delivery B. Time cost and quality C.Budget

36. When delivering a project, the project manger has to balance which of the following

A. Definition and delivery

B. Time cost and quality

C.Budget spend and contingency

Cost and scope

37. Configuration management can be used to control documents information and:

A. Users

B. Audits

C. Stakeholder

D. Assets

38. Which of the following can be adjusted in a timebox situation

A. Deadline and duration

B. Time and cost

C. Scope and quality

D. Budget and resources

40. Which of the following is a key purpose of project management?

A. Identify treat and manage project risks

B. Manage costs and make savings

C. Achieve specific objectives for change

D. Develop a robust project management plan

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!