Question: *365 days in a year* Using EOQ, Ducati motorbikes is building a plant in the US and will import the engines from Italy. Engines are

*365 days in a year* Using EOQ, Ducati motorbikes*365 days in a year* Using EOQ, Ducati motorbikes

*365 days in a year*

Using EOQ, Ducati motorbikes is building a plant in the US and will import the engines from Italy. Engines are transported between the two locations using planes and trains, with each trip costing $2,500. The motorcycle plant assembles and sells 150 motorcycles each day. Each engine costs $750, and Harley incurs a holding cost of 15 percent per year. 4. What is the Ordering Cost? 5. What is the Annual Holding Cost (hc)? 6. What is the Total Inventory Cost