Question: 37. A project team is working on the scope baseline component of the project management plan. What document should be included? A. Work breakdown structure
37. A project team is working on the scope baseline component of the project management plan. What document should be included?
A. Work breakdown structure (WBS) dictionary
B. Risk management plan
C. Cost management plan
D. Scope management plan
Your answer:
38. The planned value (PV) of a project is US$10,000and its actual cost (AC) is US$8,000. If the cumulative variance is US-$2,000, What is the cost performance index (CPI)?
A. 0.6
B. 0.75
C. 0.8
D. 1.25
Your answer:
39. During implementation of the software development project, the project manager find an important component was not included in the word breakdown schedule, but it is 10% over budget. To include the component in the revised WBS, which step should the project manager implement?
A. Report the situation to the sponsor
B. Immediately modify the WBS, add the missed component in it
C. Do not make change, it will cause over budget
D. Initiating change requests, and assess the impact of various aspects with the team
Your answer:
40. A project team collects a large number of requirements and must organize and prioritize these to complete their review and analysis. What should be used to accomplish this task? (refer to PMBOK guide)
A. Nominal group technique
B. Affinity diagram
C. Delphi technique
D. Facilitated workshop