Question: 38. Compute the relevant information and include the information on the node utilizing the PDM method. That would include calculating ES, EF, LS, LF, and

38. Compute the relevant information and include

38. Compute the relevant information and include the information on the node utilizing the PDM method. That would include calculating ES, EF, LS, LF, and TF. Mark the critical path on the schedule. All relationships are FS. Disregard the Free Float (FF) calculation. Gravel Roadway Compact Road 6 Activity ES Dur LS EF FF TF LF Set Culvert Set Entry Gate 8 10 Purchase Materials Lay Out Work Stretch Wire Move Out 4 8 Finish Grade Dig Post Holes Set Posts 8 12 Remove Trees 9