Question: 39. Given five managers i = R,S,T,U,V and five projects j = A,B,C,D,E with the following Minimization Assignment table, solve the assignment problem via Hungarian

39. Given fivemanagers i = R,S,T,U,V and five projects j = A,B,C,D,E with the following Minimization Assignment table, solve the assignment problem via Hungarian Method.

26

36

40

30

28

18

50

34

40

22

28

40

30

42

20

20

30

36

32

16

26

24

22

20

28

Based on the Hungarian method, what should be theMinimum Z* value?

Keep your written work.

Select one:

a. 120

b. 116

c. 118

d. 112

e. 114