Question: 3a) b) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time
3a)
The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time 2 8 14 18 10 11 17 What is the minimum expected completion time for the project (please round off to two decimal digits)? Your Answer: The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time 10 B O 69 18 D B | 5 11 17 What is the minimum expected completion time for the project (please round off to two decimal digits)? Your