Question: 1.a) If an activity whose normal duration is 50 days can be shortened to 32 days for an added cost of $8700, what is the
1.a) If an activity whose normal duration is 50 days can be shortened to 32 days for an added cost of $8700, what is the crash cost per period? (please round off to two decimal digits) 2) The following represents a project with four activities. All times are in weeks
Activity. Immediate Predecessor. Optimistic Time. Most Likely Time. Pessimistic Time
A. - 2 8 14
B - 8 8 8
C A 6 9 18
D B 5 11 17
What is the minimum expected completion time for the project (please round off to two decimal digits)? b) The following represents a project with four activities. All times are in weeks
Activity Imm Pre Optimistic Time Most Likely Pessimistic
A - 5 10 14
B - 8 8 8
C A 6 9 18
D B 5 11 17
What is the minimum expected completion time for the project (please round off to two decimal digits)?
Step by Step Solution
There are 3 Steps involved in it