Question: 3...Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into

3...Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into Process B. Output from B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C. Suppose further that Process A receives input at the rate of 30 per hour. Which process will be experiencing starving?

  • None of these choices are correct.
  • Process B
  • Process A
  • Process B and Process C
  • Process C