Question: Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into
Consider a three sequentially stepped process named as Process A, Process B, and Process C. Input comes into Process A. Output from A goes into Process B. Output from B goes into Process C. Output of C is the final output. Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C. Suppose further that Process A receives input at the rate of 30 per hour. Where would you place a buffer?
a) none of these choices are correct
b) in front of process b
c) in front of process a
d) in front of processes c
e) in front of both process B and process C