Question: 4 1 Point When constructing a responsibility matrix or RACI chart, it is important to ensure that only one person has primary accountability for any
4 1 Point When constructing a responsibility matrix or "RACI" chart, it is important to ensure that only one person has primary accountability for any activity. True False Clear selection Question 5 1 Point The priority of the product in agile is more significant than in traditional project management, as the outcome, or product, will drive the elaboration of the project. True E, False Clear selection
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts