Question: 4 . 1 Study house material took 2 days longer than planned. Update the schedule based on this change. Which of the following is

"4.1 Study house material" took 2 days longer than planned. Update the schedule based on this change. Which of the following is NOT true?
Note: Before you proceed to the next question, close the file without saving changes, then reopen it to return to the original schedule. OR: change the task duration back to 5 days.
The number of critical paths has changed
"4.10 Reattach house" has a new begin date of 12/26/14
"4.3 Cut house in half" remains on the critical path
"4.2 Calculate house weight" has a new end date of 12/10/14
 "4.1 Study house material" took 2 days longer than planned. Update

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!