Question: Question 2 1 pts As the project progresses, you realize that the 4 . 3 Cut House in Half task will take 2 days

Question 2
1 pts
As the project progresses, you realize that the "4.3 Cut House in Half" task will take 2 days longer than planned. Implement this change in the schedule. Which of the following is NOT true about the impact of this delay on the overall project?
Note: Before you proceed to the next question, close the file without saving changes, then reopen it to return to the original schedule. OR: change the task duration back to 5 days.
The number of critical paths will change
"2.2 Build Ramp at New Location" activity will not be affected
None of the work packages listed under the "1.0 Position Barge (Raft)" subdeliverable will be on the critical path
The scheduled completion date of the full project will be delayed
 Question 2 1 pts As the project progresses, you realize that

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!