Question: 4 1 . You are beginning a new project. When should you use the Perform Integrated Change Control process? a . Throughout the entire project
You are beginning a new project. When should you use the Perform Integrated Change
Control process?
a Throughout the entire project
b Only when closing out the project
c Only after the project is completely funded
d Only after the project scope is clearly defined
The project management team has determined that there are some changes to the scope
of the project. According to the PMBOK, who is responsible for reviewing, evaluating, and
approving documented changes to the project?
a Change Control Board CCB
b Change Configuration Board CCB
c Scope Control Board SCB
d Configuration Control Board CCB
What is the difference between the Monitor and Control Project Work process and the
Direct and Manage Project Work process
a The Monitor and Control Project Work and the Direct and Manage Project Work
processes are the same.
b The Monitor and Control Project Work process monitors the project performance
while the Direct and Manage Project Work process is concerned with performing the activities
to accomplish project requirements.
c The Monitor and Control Project Work process is a subprocess of the Direct and
Manage Project Work process.
d There is no such thing as the Monitor and Control Project Work process.
You are a consulting project manager and an investment bank has a contract with you
to run a large information technology project that is expected to last months. During the
Direct and Manage Project Work process, you discover that several regulatory requirements
were addressed in the project management plan but missed from the scope statement.
Failure to meet these requirements could result in legal action against the company.
However, implementing the technology to comply with these regulations could exceed the
budget and scope of the project and result in the cancellation of the project. What should
you do
a Do not do anything as these requirements are not a part of the scope baseline.
Service PrepaPMP FebruaryJuly Page on
b Request additional funds to implement these requirements.
c Submit a change request to incorporate the missed requirements in the project's scope.
d This is a classic example of scope creep and such requirements must be ignore
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock