4.(25 pts ) Jobs A, B, C, D, and \(\underline{\underline{E}}\) are waiting for processing at the Sawing Work center. The processing times, number of operations, and due dates for these jobs are provided below. Move and queue time is 2 days per operation remaining.
a. In what sequence should these jobs be processed using the critical ratio priority rule. Show your work.
b. In what sequence should these jobs be processed using the slack per operation priority rule. Show your work.
c. In what sequence should these jobs be processed using the earliest due date rule. Show your work.