Question: Question 2 a Five jobs, A, B, C, D, and E, arrives to be processed on the morning of January 1, 2021. PJC is scheduled

Question 2 a

Five jobs, A, B, C, D, and E, arrives to be processed on the morning of January 1, 2021. PJC is scheduled to work 7 days a week for the next 2 months. January's work for PJC consists of five jobs. A, B, C, D and E. Job A takes 3 days to complete and is due on day 9, job B takes 10 days to complete and is due on day 14, C takes 6 days to process and is due on day 8, job D takes 7 days to process and is due on day 14, and job E, which takes 5 days to process, is due on day 11.

Put together a FCFS, DDATE, SLACK, CR, SPT and a summary sequence for the above. (15 marks)

Job

Processing Time (days)

Due Date

A

3

January 9

B

10

January 15

C

6

January 8

D

7

January 14

E

5

January 11

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!