Question: 4 . 3 . 1 9 ) A tire company has two plants, one in Dallas and one in New Orleans. The Dallas plant can

4.3.19) A tire company has two plants, one in Dallas and one in New Orleans. The Dallas plant can make 800 radial and 280 standard tiers per day. The New Orleans plant can make 500 radial and 150 standard tires per day. It costs $22,000 per day to operate the Dallas plant and $12,000 per day to operate the New Orleans plant. The company has a contract to make at least 28,000 radial and 9000 standard tires. How many days should each plant be scheduled to minimize operating costs?
Dallas:
New Orleans:
Operating Costs: