Question: 4 / 4 pts When one resource required for the completion of a project is increased, yet all other factors remain fixed or decrease, that
4 / 4 pts When one resource required for the completion of a project is increased, yet all other factors remain fixed or decrease, that is referred to as the ____________. Fixed resource law,Law of optimization,Law of diminishing returns,Murphy's law