Question: 4 8 . Claire is a Project Manager for building a new apartment complex. The planning of the project is complete and an Exit Gate
Claire is a Project Manager for building a new apartment complex. The planning
of the project is complete and an Exit Gate meeting is scheduled. What is likely to
happen in this meeting?
A Project's learning will be documented and the project will be closed.
B Claires performance will be critically analyzed by the management.
C The performance of the project team members will be reviewed by Claire.
D Projects deliverables will be reviewed and a decision will be made on projects
continuation.