Question: 4 . A facility operates 8 hours per shift, 1 shift per day, 5 days per week. The standard time for the primary milling operation

4. A facility operates 8 hours per shift, 1 shift per day, 5 days per week. The standard time for the primary milling operation is 70 seconds. The efficiency of the process is 98%. The average time before failure is 30 hours. The average time for repairs is 4 hours. The product has a forecast for 43000 units per week.
a. What is the availability for the tooling?
b. How many identical workstations are needed for final assembly?
c. What would you say are some of the biggest problem areas for this line?