Question: n assembly line operates for 8 hours per shift, 1 shifts per day, 6 days per week is to be configured for a product whole

n assembly line operates for 8 hours per shift, 1 shifts per day, 6 days per week is to be configured for a product whole assembly comprises 10 tasks. The longest task is takes 8 minutes, the shortest task takes 4 minutes, and the sum of the task times is 60 minutes.
The required output is 200 units per week.
What is the maximum cycle time that will ensure meeting the weekly output? The answer is a whole number.
What is the minimum number of workstations that will ensure meeting the weekly output? The answer is a whole number.