Question: 4 . A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors ( weeks ) ( $ )
A project has the following activities:
Normal Normal Crash Crash
Immediate Time Cost Time Cost
Activity Predecessors weeks$weeks$
A none
B A
C A
D B C
E C
F D
G E F
a Draw the network diagram based on normal time.
b What are potential paths connected paths and corresponding durations?
c What is the expected project completion time based on normal time?
d What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?