Question: A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors (weeks) ($) (weeks) ($) A none 4 3,000
- A project has the following activities:
Normal Normal Crash Crash
Immediate Time Cost Time Cost
Activity Predecessors (weeks) ($) (weeks) ($) A none 4 3,000 3 5,000 B A 9 5,000 7 8,000 C A 4 7,000 4 7,000 D B, C 6 6,000 4 8,000 E C 8 4,000 6 8,000 F D 3 4,000 2 9,000 G E, F 4 2,000 2 7,000
- Draw the network diagram based on normal time.
- What are potential paths and corresponding durations?
- What is the expected project completion time based on normal time?
- What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?