Question: 4. A project manager is using the Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1 a)
4. A project manager is using the Project Network Diagram to perform critical path analysis. The diagram is represented as shown in Table 1

a) Draw a network diagram representing the project b) What is the critical path for this project and how long does it take? c) What is the shortest time in which this project can be completed?
Activity number Activity name Duration in hours Predecessor 1 Date/Location 1 2. Hotel booking 25 1 3 Arrival 15 1 4 On-site offers 20 1 LO On-site program 10 4 6 1 2,3,4 Send info to participants Approval 7 30 5,6 8 Event start 5 7Step by Step Solution