Question: 4. A work sample taken over a 100-hour work month has produced the following results: UnitsproducedIdletime(notpartofthetask)PerformanceratingAllowancetime(basedonworkingtime)20025%110%15% What is the standard time for the job
4. A work sample taken over a 100-hour work month has produced the following results: UnitsproducedIdletime(notpartofthetask)PerformanceratingAllowancetime(basedonworkingtime)20025%110%15% What is the standard time for the job