Question: 4) Based on the information provided perform the relevant calculations (EV, PV, AC, CV, SV, CPL, SPI, EAC, ETC) to determine the position of

4) Based on the information provided perform the relevant calculations (EV, PV, AC, CV, SV, CPL, SPI, EAC, ETC) to determine the position of the project. Explain the position of the project. Please round your answers to 2 decimals places (12 points) Tasks A B D I A B Dependants Project Progress Report at the end of day 3: D none Starts at the same as A A (Finish to start relationship) B (Finish to start relationship) Task % Completed 100% 65% 15% entire task Not Started Duration (days) 2 3 3 40 100 310 Cost (BD) 50 100 210 100 Actual Cost
Step by Step Solution
There are 3 Steps involved in it
Answer To determine the position of the project we need to calculate several key metrics based on the provided information EV Earned Value PV Planned ... View full answer