Question: 4. Develop a 10 day production schedule, starting with Tuesday, March 19 and then convert them to actual production orders. As we discussed in class,
4. Develop a 10 day production schedule, starting with Tuesday, March 19 and then convert them to actual production orders. As we discussed in class, Production has to schedule the recommended planning orders in such a manner that production capacity (16,000 a day) is fully utilized and set-up costs are minimized. Every time you change package sizes, you will incur delay and setup costs